Working and building near our assets
If any construction activity is to occur over an easement vested in GWMWater or within 1.5 metres of a GWMWater asset, prior approval should be sought from GWMWater. Please contact us via our website or by emailing info@gwmwater.org.au
A Build Over Easement Agreement is usually required and can involve the establishment of additional easements to maintain access.
Applications should proceed with minimal delay and inconvenience when these steps are followed:
1. Determine if there is an applicable easement
2. Request a detailed sewer or water asset plan from GWMWater
3. Comply with the requirements specified in the Build Over and Adjacent to GWMWater Assets Guidelines
4. Lodge an application along with a set of building plans and the application fee
Further information can be found in the Build Over and Adjacent to GWMWater Assets Guidelines.